An integral core team is the foundation

In 2006, the Public-Private Partnership (PPP) for the renovation of the Ministry of Finance in The Hague was the first DBFMO contract for the Dutch government. This meant a different type of solicitation. Instead of prescribing everything, the market was given the freedom to offer the best solution. This means that the client must explicitly state what functional requirements the system must meet. On the other hand, the consortium must demonstrate that the solution truly meets this. Sietske Bergsma, Martie Jacobs and Angelia Zeegers were on the core team that prepared this tender. They look back fondly on their exploration and are proud of the results.

The first performance contracts within government emerged in the early 1990s. For this type of contract, it is crucial to explicitly describe the problem to be solved. You must always determine what is really important. In this new situation, it was important to describe well what we wanted to see, without naming the solution itself. There is always a tension here between taking acceptable risks and allowing room for creativity. The trick is to keep the question functional while still maintaining an overview.

Fresh perspective

Choosing an integrated contract means specifying the demand in context. Here it is important to take time at the front end to keep the output specification as pure as possible and to convey the client’s interest and goals as clearly as possible. Therefore, we chose to draft the specification with a small core team. This is because the risk of involving too many people and specialists is that you’ll still record a lot in advance or get into the details too quickly. This is always at the expense of the consortium’s creative freedom, when their fresh perspective was precisely what was desired.

So it is very important to formulate the question cleanly and sharply and keep an eye on the greater goal. Here, of course, the user plays a key role; they must ultimately be able to function pleasantly in the building. The premise was also that we determined the demand with the user rather than for. Therefore, a focus group with users was the starting point.

“The trick is to keep the question functional while still maintaining an overview.”

Providing space

In drafting the requirements, we deliberately left room for the contractor. For example, by requiring that the green character be preserved. The building had two courtyard gardens, which management did not want to cover. Such upfront constraints don’t belong in a DBFMO contract, and so we put a stop to that. In part because integral consideration was given to both functionality and aesthetics, the courtyard garden was ultimately covered, and mezzanines were incorporated. The result now fully meets the original requirement and fits well with the actual use and service needed or expected.

This includes, for example, moving the entrance. That was not the intention at first. We also got a single reception. By looking at the task integrally, the consortium chose this solution. By positioning one entrance at the center of the building, you will save the cost of a second staffed reception desk for 25 years. Precisely by not stipulating everything in advance and daring to take acceptable risks, these solutions do go the extra mile.

As a procurement team, we worked together intensively and tried to properly identify all interfaces in addition to the requirements. All efforts to get the requirements and connections right initially resulted in a bulky paper traditional Requirements Specification. This specification contained requirements on design, construction, maintenance, operation and facility services that were recorded in various documents. The goal was a unified specification in which all perspectives, requirements and interrelationships were clearly defined. However, it was difficult to get a grip on such a large amount of information.

Do you want to discover more lessons learned?

This article is part of a collection brought together in this book, based on interviews and practical experience from the construction industry.

Added value of models

Fred Lohman and Juriaan van Meel then got involved and helped translate the output specification into a digital model. They first ran a pilot that immediately showed the added value of their model. Different definitions for the same objects had crept into the specification. This was confusing and could cause ambiguity and discussions later in the process. In addition, conflicting requirements came to light. These, too, could result in additional costs. With a digital model, it was easier to formulate the requirements unambiguously. Another advantage was that we only had to specify the building blocks such as spaces, inventory and functions once and then could relate the appropriate requirements to them. That saved time. The experiment we undertook at the Ministry of Finance with a digital model proved its added value to such an extent that the Central Government Real Estate Agency decided at the time to use the model for all integrated contracts.

No fill-in-the-blank exercise

Using a digital model for the output specification, which includes the user, was very helpful. It provided structure and overview because everything was traceable. However, it is important here that a small core team directs input into the model. At the same time, we did have to constantly find the right balance in the application. It is effective if all parties work in the same model, but the intention is not to force users. Moreover, a tool can also be a risk because you stop thinking about the context. In our view, dogmatism does not work; you should always keep thinking about what is actually needed and what the user needs. Who is not interested in the process and only looks at the result. Only when this is all clear do the model and requirements come into play. It is never an automatic fill-in-the-blank exercise.

With this form of contract, we entered a new world and it was certainly not easy to find the right way. With Systems Engineering, we at least had a good foundation for examining the demand and going through the process from A to Z. It was hard work, but the result is worth it. We still enjoy that as a team every day when we are in the Finance Ministry building.

Lessons learned

  • Find the balance between harnessing the creativity in the contractor and ensuring that the chosen solution deviates too much from the demand.
  • Check that the solution in the solicitation is also the solution for the user.
  • Create the output specification with a core team and limit the involvement of specialists.
  • Always consider the context when creating an output specification in a digital model.
  • Record output specifications in the form of a digital model to formulate requirements unambiguously and without contradictions.
  • Know that the user is interested in the functioning of the solution, not the solution itself.
Biography

Sietske Bergsma

Sietske Bergsma started her career as a consultant with KPN Real Estate and Facilities. From 2002, she was project manager on behalf of the Ministry of Finance on the PPP renovation of Finance. From 2009 to 2015, she was self-employed and supervised projects for various government organizations, as well as Nuon and Facilicom. As of 2015, Bergsma is employed by the Central Government Real Estate Agency as project manager for the RIVM and for the realization phase of JC Zaanstad.

Martie Jacobs

Martie Jacobs studied Architectural Engineering and obtained a master’s degree in facility management. In her career, she developed from a architectual consultant to a senior consultant and project manager of complex processes. In the PPP renovation of the Ministry of Finance, she was a technical team consultant. She also worked on housing and renovation projects for various ministries, the municipality of Rotterdam, the municipality of Eindhoven and the province of Gelderland, among others. Currently, Jacobs is a partner at Republiq.

Angelia Zeegers

Angelia Zeegers started as a technical advisor with the Central Government Real Estate Agency in 1991. She is currently involved as a coordinating/specialist advisor in various developments regarding integrated contracts such as the PPP renovation of the Ministry of Finance in The Hague, PPP Detention Center Rotterdam, DBM Tijdelijke Rechtbank Amsterdam, DBM Herman Gortercomplex Utrecht and Maincontracting DJI.

Relatics - Pioneers in Systems Engineering

Pioneers in Systems Engineering
Insights and lessons learned from construction industry professionals.