In this article, experts discuss how Systems Engineering is applied in real construction projects, highlighting lessons learned and difficulties encountered over years of experience.

Don’t make it harder than it is

Harry op ‘t Ende has gained experience primarily as a project manager in the industrial and energy sectors. When he encountered Systems Engineering in the infrastructure sector on the De Groene Loper project for the A2 highway in Maastricht, he experienced the added value of the method. He did notice that the demonstration of requirements compliance focused mainly on paperwork and less on the quality of the product to be delivered. He was not used to that in the industrial sector. There, the goal is to get a plant up and running as quickly as possible, and that can’t be done without multidisciplinary work, with an eye for interfaces and a reliance on craftsmanship.

Systems Engineering is a methodology for agreeing on a clear structure and formulating requirements. I see that as a bit of expectation management. You define the requirements on the front end and, as the client, indicate when you are satisfied. It is up to the contractor to demonstrate this adequately. In doing so, do not slip into a demonstrability crunch. Then you lose sight of what is at stake and just create a paper tiger. In this context, I am always in favor of common sense rather than ticking boxes.

In my view, a client should just ask for what they want and only set requirements if the solution is not yet known. If you do have a solution in mind, ask for it. That saves everyone a lot of time. I advocate including only requirements that you want to explicitly manage. With a tunnel, there are often thousands of requirements, of which only 300 are really important. You must then have the courage to focus on the requirements that are important and meet them properly.

“Information is more readily available, which helps decision-making.”

Professionalism and confidence

An example. In the industrial sector, for example, security of supply is important, and you achieve that with 95% availability. This requires a certain redundancy of systems. I don’t think how that is implemented needs to be defined in the requirements. Skilled engineers can figure that out just fine by mutual agreement. In that case, that 95% availability is a sufficient basis for the contract. Derived requirements often create a gray area. This is where the project manager’s professionalism and confidence come into play. You need professionals in all areas and must dare to rely on the technical people or at least make sure they help each other. Professionals know what they can do; it is not effective to restrict them because they must absolutely meet requirements.

Multidisciplinary approach

Furthermore, in the process, reliability, safety and interfaces must be in order and known. You have to find common agreement on that on the front end. This is why I favor multidisciplinary review sessions at the beginning of a project. If you work with the client on day one to define the acceptance criteria and demonstrate how you will achieve them, you have a good foundation. There is then commitment to the outcome, the processes are clear, and the entire chain is aligned. In essence, the client is then already satisfied. So you should not wait with this until just before delivery.

Do you want to discover more lessons learned?

This article is part of a collection brought together in this book, based on interviews and practical experience from the construction industry.

Utilizing capacity

In recent years, though, it has been nice that digitization has provided acceleration in the process. Information is more readily available, which helps decision-making. It is also much easier that data can be visualized. But again, don’t overdo it. It does not make sense to start visualizing everything. Then you miss the mark. As with setting requirements, the key is not to push things too far. Especially at a time when capacity is scarce, we need to make the best use of the knowledge and experience that is available.

Lessons learned

  • Define requirements only if the solution is not yet known or in your mind.
  • Be critical in the amount of requirements, leave the detailing to the professionals.
  • Organize multidisciplinary review sessions to establish reliability, safety, interfaces and expectations.
Biography

Harry op 't Ende

Harry op ‘t Ende studied Chemical Engineering at the University of Groningen. After this he went to work for Gasunie, an energy network operator, where he was a process technologist and project manager. After an intermediate step as a project manager at KEMA, he worked on large-scale industrial projects at NBM Amstelland. Since 2007, he has been the founder and co-owner of PRO6 managers. From this organization, as project director, he was involved in the Avenue2 project (A2 Maastricht tunnel), among other things, and responsible for the development and realization of sustainable energy projects both domestically and abroad.