In this article, experts discuss how Systems Engineering is applied in real construction projects, highlighting lessons learned and difficulties encountered over years of experience.

Throwing it over the fence

According to Harro Verhoeven, information management is key within Systems Engineering. In his view, however, when recording data in the process, the emphasis is too much on the project. As a result, the information generated in the design and construction phase is of limited use for managing objects in public spaces. And unusable or incomplete information makes effective management especially difficult.

In practice, the prior history of objects in the outdoor space, which must be managed or maintained by municipalities, for example, was recorded in a fragmented way. The worlds of the parties involved are separate. As a result, information is scattered and stored separately from the whole with the designer, contractor, supplier and asset manager. These are all specialists with their own data, managed in their own systems.

“Information was also frequently lost in the transfer between project phases, resulting in a lot of duplication in the use phase.”

Avoiding duplication of effort

Although the asset manager plays a crucial role in the use phase of an object or system, in the past it was mainly a matter of waiting to see how the relevant management information was transferred. It was common for information to be more or less thrown over the fence after transfer. Information was also frequently lost in the transfer between project phases, resulting in a lot of duplication in the use phase. At the end of a lamppost’s life cycle, for example, it was not clear exactly what type of light pole it was, with what connection and how many lumens were originally agreed upon. The asset manager did not have this information, and that meant that all the data had to be retrieved in case of failure or replacement.

I see the solution direction similar to the national Electronic Health Record (EHR) developed in the healthcare sector, but then for all objects in the outdoor space. Previously, general practitioners, hospitals and healthcare facilities kept their own records of their patients. It was unclear exactly what they were recording, and data exchange was complicated. The development of a national EHR required all healthcare providers to record and make available patient data according to a national standard, which greatly improved the exchange of medical data. At CROW, we want to achieve the same for the civil engineering sector: with the Public Space Management Information Model (IMBOR), we are developing a data standard to start sharing object data uniformly within the asset management process.

Do you want to discover more lessons learned?

This article is part of a collection brought together in this book, based on interviews and practical experience from the construction industry.

The entire life cycle

My basic premise is that the object in the outdoor space should always take center stage. This can then act as the coat hanger you hang all the information on. That means you opt for object-oriented design, construction and management. If you capture and make object data standardized and available right from the start, you can easily keep the data together during contract creation, execution and operation and maintenance. Asset owners then always have access to the right information to perform their asset management tasks optimally. Standardized recording of object information also avoids confusion over definitions. For example, a contractor now talks about an asphalt layer, while an asset manager talks about a road section of X number of meters. If we manage to unify this, it will save a lot of research and discussion. I am convinced that this enhances the quality of the outdoor space.

Lessons learned

  • During the project, actively pay attention to information transfer for the asset management phase.
  • Centralize the object to be managed as a coat hanger for all relevant information.
  • Record object data in accordance with data standards to prevent misinterpretation and data loss.
Biography

Harro Verhoeven

Harro Verhoeven studied Applied Mathematics at the University of Twente. He then joined the province of Utrecht as senior road policy officer. After an intermediate step as a consultant at ECORYS, he started as a project manager at CROW in 2001, an independent knowledge center for governments, contractors and engineering firms. Here he was involved in the development of the Public Space Quality Catalog, among other things. He is currently working on the creation and rollout of the Public Space Management Information Model (IMBOR).